Hub Progress

MVHS HUB – Progress Update

Period: November–December 2025 • Report date: 21 December 2025

Celebrating Our Achievements

  • Basement retention completed and inspected with Regulation 126 compliance – a key structural milestone enabling vertical works.
  • Bulk excavation finished on schedule despite challenging conditions.
  • Community-first actions: clean roads and footpaths, upgraded nature strips, and compliant stormwater controls.
  • Constructive collaboration with Conyer Street community, childcare operators, and local businesses.
  • Design rigor: transparent tracking across disciplines; permits secured amid evolving requirements.
  • Safety & quality excellence: zero incidents this period; no QA non-compliances reported.
  • Financial discipline: procurement gains offset expected overrun; clear monthly cashflow planning.

Executive Summary

Overall project health: Progressing with proactive risk management.

  • Bulk excavation complete; basement retention successfully achieved and certified.
  • Transitioning from foundations to building systems and vertical construction.

Contracts & Key Trades

Retention
Gudbuilt Civil – ~98% complete.

Vertical Transportation
Direct Lifts – shop drawings approved; lifts in manufacture. ETA delivery: June 2026.

Hydraulics & Civil Drainage
Time Plumbing – underground works targeted by 21 Jan 2026.

Mechanical
D and B Mechanical Services – recommended for award.

Electrical
Rajah Electrics – recommended for award.

Dincel Walls
Davmar TRT Contractors – recommended for award.

Reinforced Blockwork
JOYA – negotiations ongoing (labour only).

Scaffolding
Scaffright – negotiating lump-sum for project duration.

Construction Program (Dec 2025 – 15 Feb 2026)

  • Civil drainage, underground tanks & detailed excavation
  • Lift pit construction; foundations & columns
  • Partial scaffolding to stairs area
  • Dincel wall shop drawings, installation & concreting
  • Slab on ground; formwork for suspended ground floor slab

OH&S: No safety issues recorded; regular toolbox meetings ongoing.
Quality: No non-compliances reported.

Community & Stakeholder Engagement

We continued proactive engagement with neighbours, local groups and authorities. Roads and footpaths were kept clean during bulk excavation; nature strips upgraded; stormwater controls implemented to Victorian standards. Regular conversations with the Conyer Street community, childcare operators and local businesses help maintain trust and collaboration.

Financial Snapshot

  • Target budget: A$5.2M (ex GST)
  • Potential variations (approx.): ~A$150k

What’s Next

  • Commence post‑tensioned slab works mid‑January 2026.
  • Finalise awards for mechanical, electrical, Dincel walls, blockwork and scaffolding.
  • Maintain design coordination and regular community updates.